| Land Use |
Acres |
| Cropland/Hayland |
3,149 |
| Pasture
(Irrigated/Domestic) |
49 |
| Rangeland |
26,162 |
| Forest/Woodland |
3,093 |
| Chaparral |
8,516 |
| Urban |
3,389 |
| Other |
4092 |
| Total acres in
watershed |
48,450 |
Problem
Identification and Watershed Planning
Erosion in the watershed was seen
as a problem by many observers through the years. The Coastal San Luis
Resource Conservation District (RCD) had long recognized the importance
of the Morro Bay Estuary. In the 1970's District leaders adopted the
reduction of erosion in the Morro Bay watershed as one of their long
term goals. In 1987 the RCD obtained funding through the California
State Coastal Conservancy (SCC) to quantify the historical loss of open
water in the bay, and to locate and quantify sediment sources to the bay
in order to create a baseline for future reference. The results of the
study indicated that the bay had been filling in at a rate ten times
greater during the last one hundred years than it had previously (Haltiner,
1988). The results also showed that the bay has decreased in volume by
25 percent in the last century (Haltiner, 1988). The major source of the
sediment is the brushlands in Chorro and Los Osos Valleys. Chaparral
covers approximately 19% of the 48,450 acre watershed. However, it
contributes 30% of the sediment to the bay. Conversely rangeland covers
60% of the watershed, yet contributes only 17% of the sediment to the
bay (USDA SCS, 1989).
Using these studies as a baseline
the RCD then hired the USDA Soil Conservation Service (now known as the
Natural Resources Conservation Service) to develop the Morro Bay
Watershed Enhancement Plan. The recommended plan detailed three phases
of action. Phase I was land treatment. Phase II was a sediment trap on
Los Osos Creek. Phase III was a sediment trap on Chorro Creek.
Phase III of the Mbwep is the
Chorro Flats Enhancement Project (CFEP): which is a sediment capture,
agricultural preservation, habitat restoration and education project.
The CFEP has essentially reconnected Chorro Creek with its historical
floodplain, thereby allowing sediment to be deposited there instead of
in Morro Bay. This is the most significant single action included in the
plan. It was estimated that 35% of the sediment entering the Bay through
Chorro Creek could be caught by a sediment trap at this site (USDA SCS,
1989).
Site
Description
The 129 acre site located at the
intersection of Quintana Road and South Bay Boulevard near the city of
Morro Bay was once known as Chorro Cienaga (swamp). At that time, under
the dense vegetation of willows and other riparian species, when Chorro
Creek flooded, the water spread over the land and dropped sediment. Rich
alluvial soils were created by this process and millions of cubic yards
of sediment were trapped here rather than being carried into the bay.
In the 1950’s Chorro Creek was
confined by a levee to a narrow channel along the southern edge of the
property. This allowed the adjacent land to be used for growing
vegetable and hay crops in the rich stream deposited soils. But the
sediment-rich water flowing downstream was no longer able to spread out
and deposit its load on the floodplain as it had been doing for eons.
Instead, the sediment remained suspended until it reached the estuary,
where much of it was trapped.

Figure
2: Site Plan
Site
Acquisition
The Morro Bay Watershed
Enhancement Plan recognized that the Chorro Flats site would be an ideal
place to trap sediment before it reached the Bay. Fortunately, about
that time the Domenghini family that had owned and farmed the site for
years put the land on the market. Carol Arnold of the State Coastal
Conservancy entered into negotiations with the family, and after two
years of on-again off-again negotiations entered into an agreement with
the owners to purchase the land. Carol Arnold put together a package
where the Conservancy would provide funds to the RCD to acquire and
restore the site. The purchase price of $1,450,000 required more funds
than those available to the SCC at that time, so Ms. Arnold applied for
and received $800,000 from Proposition 111 funds, administered by Cal
Trans. The RCD received the title for the land on December 18, 1991, and
immediately began the planning process for the CFEP.

Figure
3: Aerial Photo of Site and Vicinity
Project
Planning
The Chorro Flats site is especially suitable for
sediment trapping because:
- Chorro Creek runs through the site;
- Chorro Flats is at the terminus of the watershed;
- Chorro Flats is relatively flat and well suited to
trap sediment;
- The site historically was a floodplain, covered
with riparian vegetation that naturally trapped sediment.
Sediment control was the principal
reason behind the acquisition of the property, however the RCD and the
SCC recognized that a number of other important natural resources on the
site could be protected and enhanced. These resources include the
aquatic habitat and fisheries, the riparian habitat and wildlife,
groundwater, agricultural use and water quality and quantity.
After receiving another grant from
the Coastal Conservancy, the RCD hired consultants to prepare an
Enhancement and Management Plan for the site. Several preliminary
studies preceded the preparation of the final plan. The first report was
an assessment of the planning area covering topography, hydrology,
groundwater, soils, agriculture, vegetation, wildlife, fisheries,
archeology, easement, and regulatory polices applicable to the site. The
results of this study were published in the Existing Conditions
Background Report.
During all phases of the planning
process extensive public input was encouraged. Several public meetings
were held. The Morro Bay Task Force was involved in the planning
process. A Technical Advisory Committee composed of members of the
public, the California Department of Fish and Game, the State Department
of Parks and Recreation, the Regional Water Quality Control Board, the
County of San Luis Obispo, the City of Morro Bay, the U.S. Fish and
Wildlife Service, the Army Corps of Engineers, the SCC, the NRCS, the
National Estuary Program, the Sierra Club, the Friends of the Estuary
and neighbors of the site met on a regular basis to discuss and decide
on issues.
Next, specific goals and
objectives for the plan were articulated. These related to sediment
trapping, agriculture, fisheries and wildlife enhancement among other
topics and are published in a report entitled Goals and Objectives
for Chorro Flats.
The consultant team developed
three alternatives for the site. These alternatives were considered and
discussed at a number of public meetings. Alternative one emphasized
agriculture and devoted more of the site to that purpose. Alternative
two increased the size of the floodplain, while still maintaining a
viable agricultural parcel on a portion of the site best suited for
farming. The third alternative included an active sediment removal basin
that would require periodic dredging of a sediment basin located off the
main channel of Chorro Creek. This alternative would have resulted in
some negative impacts related to fisheries, maintenance costs and
aesthetics.
These alternatives were presented
in the Analysis of Options and Alternatives Report, and they were
discussed at a number of public meetings. The public and the Technical
Advisory Committee overwhelmingly favored alternative two. The final
plan was based on this alternative although adjustments and refinements
occurred in the final detailed planning. The final plan was published in
April of 1994 and was titled: Conceptual Plan, Chorro Flats
Enhancement and Management Plan.
The passive sediment trapping
system allows sediment to accumulate on the floodplain as a result of
deposition during overbank flows. Increased vegetation on the floodplain
helps to reduce the velocity of overbank flows and increase the rate of
sediment deposition. Approximately 83 acres were included in the
floodplain and 45 acres were reserved for agriculture. This allowed for
a capacity of in excess of 600,000 cubic yards and a projected lifespan
of at least 50 to 70 years. The deposited sediment will primarily be
sand sized particles with a moderate amount of fine grained materials
(silt and clay). Most of the coarse grained material (pebble and cobble)
will be trapped in the creek channel. See Figure 4.

Figure
4: Simplified Chorro Flats fluvial processes, pre- and post-construction
Interim
Site Development
Not long after the completion of
the Conceptual Plan, the August 1994 "Highway 41 Fire"
erupted. The fire burned 9700 acres, or 35% of the Chorro Creek
watershed. The area that burned was the steep brushy areas of the Santa
Lucia Range (Cuesta Ridge). Slopes as steep as sixty percent were left
denuded of protective vegetation. The RCD took advantage of a federal
program administered by the NRCS called Emergency Watershed Protection (EWP).
An EWP project was completed at Chorro Flats. To reduce the potential
for sediment conveyance to Morro Bay, the NRCS improved the sediment
trapping capability of Chorro Flats by creating a 450 foot breach of the
levee and stockpiling the material in a berm perpendicular to the
channel.
In an exceptionally rare
combination of extreme events, this major fire was followed by the most
extreme floods of record the following winter. In mid-January and again
in mid-March intense rainstorms produced tremendous flows in Chorro
Creek. The 2 to 3 day rainstorms producing these flows had a recurrence
interval of between 100 and 1000 years (Jim Goodridge, former State
Climatologist). Flood debris left on the radio towers at Chorro Flats
was more than thirteen feet above the ground surface.
It should be recognized that the
sediment trapping that occurred on the site following the 1995 floods
represented a significant benefit to Morro Bay and provides validation
for the acquisition of this site. It also presented an opportunity to
further refine the conceptual plan. A geomorphic review team recommended
that the existing Chorro Creek alignment be allowed to remain as the
primary flow channel. They further recommended that the primary
restoration approach should be to remove the existing levee, construct a
new berm far away from the channel and excavate a shallow swale to
encourage some channel overflow and provide a secondary channel location
for the inevitable channel avulsion.
The location of the overflow
channel was modified so that the connection to Chorro Creek would occur
at Chorro Creek Road. This location scoured severely following the high
flows of the early and mid 90's, indicating that geomorphically, this
was an alignment the channel wanted to take. Additionally, the ecologic
impact and permitting issues were easier here, as there were fewer trees
and impacts. Also, it made better use of the upstream and higher
elevations of the site for sediment capture.
Project
Implementation
Design
In 1996 work began on the final working drawings and the specifications
for the construction contract. Plant ecologists and restoration
specialists worked on developing the planting program. Only plants
native to the watershed were selected. The planting was to be done in
bands adjacent to the new channels in order to promote the riparian
corridor and get it established prior to the expected channel avulsion.
The ground in between the plants and the wide areas beyond the planting
zones were to be planted with native grasses. The final plant count was
over 10,792 plants including 211 Red-osier dogwood trees, 431 California
sycamores, 845 Black cottonwoods, 72 Coast live oaks and nearly 8900 red
and arroyo willows. Additionally, wax myrtle, coffeeberry, gooseberry,
California wildrose, blackberry, twinberry, hummingbird sage and
elderberry were selected. The native grass mix included California
brome, blue wildrye, meadow barley and creeping wildrye.
Additional Funding
The RCD also applied for funding from the State Water Resources Control
Board and was granted $300,000 for construction and maintenance of the
project. Carol Arnold and the Coastal Conservancy once again came
through with funding to implement the project. Carol applied for and
received $300,000 from Cal Trans, and the Coastal Conservancy
contributed $170,000 toward the construction and maintenance
costs.
Permits
After a lengthy and interesting process of acquiring all the needed
permits from the permitting agencies including; the County of San Luis
Obispo, the City of Morro Bay, the Army Corps of Engineers, the
Department of Fish and Game, the U.S. Fish and Wildlife Service, the
National marine Fisheries Service, the Regional Water Quality Control
board and the Air Pollution Control District the CFEP was ready to go
out to bid.
Construction
Whitaker Contractors of Santa Margarita was the contractor selected to
construct the project. Work began in July of 1997, five and one-half
years after the RCD acquired the land. Whitaker was a very good
contractor and the work proceeded very smoothly and was performed on
time and on budget. The planting subcontractor completed the last of
their work in late November of 1997. At the beginning of December when
viewed from Black Hill the Chorro Flats Enhancement Project looked very
much like the finished engineering drawings.
Monitoring
and Maintenance Planning
A monitoring and maintenance plan
(M&M plan) was developed in 1998 by the CSLRCD, and approved in July
of that year by the RWQCB, the U.S. Army Corps of Engineers, and the
State Coastal Conservancy. (See Appendix A.) The M&M plan was
produced to comply with permit requirements; to track and address
localized problems of erosion, revegetation needs, and other
modifications identified as the project matures; and to assess the
overall success of the project in meeting its goals and objectives. The
M&M plan specified short-term activities planned for the first two
years following construction and long-term activities planned for the
next five years. Long-term monitoring activities are planned to measure
deposition, document channel morphology changes, and monitor riparian
vegetation establishment. Long-term maintenance activities are planned
to focus on establishment of riparian vegetation, promotion of stable
stream banks, and maintenance of roads, berms, and other improvements.
These activities will initially be funded from a combination of grants.
With time, as monitoring and maintenance needs decrease, rental income
from of the agricultural portion of the site and the radio towers will
be used for these activities.
Maintenance
Chronology
Beginning in May 1998, the
California Conservation Corps (CCC) performed the initial maintenance on
planted materials: hand weeding, clearing, building irrigation basins,
watering, and placing mulch. The typical procedure is illustrated in
Figure 5a through 5d.
| Figure
5a. First you must find the plant. In this case a cottonwood. |
Figure
5b. Then clear away competing plants using hand tools. |
| Figure
5c. After the irrigation basin is formed, approximately 2
gallons of water are applied. |
Figure
5d. The finished site includes 3 inches of mulch and a flag to
aid future identification. |
Figure
5: Typical Plant Maintenance Procedure, May – June, 1998
In June, Dr. Brian Dietterick and
some of his resource management students from Cal Poly installed
"willow mattresses" along portions of the new channel
"A". See Figure 6.
|
Installation of the willow
mattress 5-29-98.
|
View from same location
9-25-98.
|
|
View from upstream side
5-29-98.
|
View from upstream side
9-25-98.
|
Figure
6: Willow Mattress - During Installation, May 1998, and after 4 months.
In June 1998, a landscape
contractor applied herbicide to control weeds (hoary cress, German ivy,
and castor bean) found on site.
All of the shrubs and trees that
were planted in 1997 were maintained through the summer of 1998 by
periodic mowing and hand weeding, and by periodic irrigation.
In September, 1998, two sections
of stream bank were intensively planted with willow fascines to enhance
bank stability.

Figure
7. CCCs installing a willow baffle, September, 1998.
In October 1998 fire-breaks were
mown around the grassland areas.
In October 1998 "No
Access" signs were installed.
During December 1998 1087 trees
and shrubs were installed by a landscape contractor.
Grassland portions of the site
were mown in January, April, June, and July 1999.
During April, May, and June 1999,
trees and shrubs planted as part of this project continued to receive
periodic maintenance by CCC crews, as needed, including hand-weeding,
mowing, basin re-building, mulching, and irrigation.
Figure
8. Irrigation continued in 1999.
In June 1999, and again in July,
an herbicide (Garlon) was applied to German Ivy growing along the old
creek channel, and to patches of Arundo donax, pampas grass, and
castor bean found near the northern most radio tower and near the
junction of the old creek and Channel B.
During June 1999, eleven raptor
perches have been installed within the riparian zone along Chorro Creek,
to enhance rodent control.
During June and July 1999, willow
stakes were installed by CCC crews at the base of some vertical banks
along Chorro Creek. The purpose of these planting is to help stabilize
the banks and increase deposition.

Figure
9. Willow wattles installed in 1999.
In November 1999, 415 trees and
shrubs were planted by Dave Fross’ Habitat Restoration class from Cal
Poly.

Figure
10. Replanting in November, 1999.
In November 1999 two willow
mattresses were installed by Brian Diettricks’ Watershed Management
class from Cal Poly.

Figure
11. Willow mattress installation 1999.
Approximately 15 acres of
grassland were replanted with native grass seed and mulched with rice
straw in November 1999. A filter strip of native grasses was planted
between the agricultural fields and the swale that drains these fields.
The remaining grasslands on site
were mown in December 1999.
Revegetation efforts associated
with the newly installed instream habitat improvement structures were
completed in December 1999.
Due to continued dry conditions,
trees, shrubs, and willow mattresses were irrigated in late November,
and again in late December 1999.
Aquatic
Habitat Improvement Structures
During September and
October 1999, 12 log and boulder structures (5 pair of opposing wing
deflectors, 1 single wing deflector, 2 mid-stream boulder clusters, and
4 log and boulder structures) were installed in the upstream portion of
the project to improve steelhead trout summer rearing habitat. The work
was partially funded by a $30,000 CDFG fisheries restoration grant, and
followed procedures in the DFG California Salmonid Stream Habitat
Restoration Manual. Rock for the project was imported from local
quarries to the project site. Some root wads which were installed into
the banks in 1997, and which were too high to function properly, were
removed and used for this project. Additional root-wads and logs were
supplied by Morro Bay State Park. Logs and large rocks were placed in
the stream bed using rubber wheeled heavy equipment.

Figure
12: Instream Habitat Improvement Structures Installed in 1999.
Photographs were taken to document
conditions before, during, and after construction, and will be taken
again in subsequent years. See Figures 13 and 14 below. (This effort
complements the photo documentation which is part of the ongoing CFEP).
Each spring, the integrity and functionality of each structure will be
evaluated, and each structure will be repaired or modified as needed.

Figure
13. Instream habitat structure installation, 1999.

Figure
14. Opposing wing deflector after installation.
An instream fish habitat survey
was conducted by the Department of Fish and Game in the summer of 1998.
Another survey will be conducted using DFG protocols in the summers of
2000 and 2002 to compare pre- and post-project conditions. (This survey
work is included as part of the ongoing CFEP.)
Results of the habitat survey, and
experience gained during installation and maintenance of the structures,
will be used to plan additional habitat improvement structures. A CDFG
fisheries restoration grant has been secured to partially fund this
habitat improvement effort for an additional two years.
Monitoring
Results
Monitoring activities were
designed to answer the following "big" questions:
• How much sediment is being
collected?
• Is a riparian plant
community developing?
• Is the stream developing a
dynamically stable configuration?
• Is habitat suitable for
endangered species being created?
• Are beneficial uses being
enhanced or is water quality being improved?
The answers to these questions are
discussed in the sections that follow.
Sediment
Collection
Approximately 23% of the total
load, and 85% of the bed-load, from Chorro Creek between 1992 and 1998
was captured on Chorro Flats (Robbins and McEwen, 1999). This trapping
efficiency was determined by
·
modeling sediment loads to the upstream end of Chorro Flats; and
then
·
measuring the volume of sediment collected;
·
using sediment samples to estimate the particle size distribution
and mass of the collected material; and then
·
comparing modeled sediment loads to estimated amounts of sediment
captured.
Monthly precipitation from July 1992
to June 1998 is shown in Figure 15.

Figure
15: Monthly precipitation between July 1992 and June 1998.
Total sediment loads to Chorro
Flats from Chorro Creek were modeled based on flow rates measured at a
gage on Walters Creek, a tributary to Chorro Creek. Annual total
sediment yield and bed material yield for the Chorro Creek watershed has
been estimated for the 1993 through 1996 water years. Additionally, the
long-term average annual total sediment yield for the watershed has been
estimated to be 60,689 tons, with an average annual bed material yield
of 6,980 tons (Tetra Tech, 1998). These modeled estimates are listed in
Table 2.
Table 2: Estimated
Sediment Loads to Morro Bay from Chorro Creek
| Water Year |
Estimated Total
Load, tons |
Estimated Bed
Material Load, tons |
| 1993 |
43,040 |
11,225 |
| 1994 |
277 |
165 |
| 1995 |
734,891 |
49,063 |
| 1996 |
20,777 |
5,294 |
| 1997 |
60,689* |
6,980* |
| 1998 |
60,689* |
6,980* |
| Total Load |
920,363 |
79,707 |
(* Long-term average values)
(**Bed material consists of particles which are
larger than very fine sand particles, 0.074 mm.)
The volume of sediment which was
collected on site was measured as follows. Topographic surveys were
conducted in 1992 (EDA, 1997) and early 1999 (Vaughan Surveys, 1999).
Comparison of this topographic data showed that approximately 188,000
cubic yards (over 213,000 tons, assuming 84 lb/cubic foot) of sediment
were collected on site during this time. A topographic map comparing
1992 to 1998 elevations is shown in Figure 16. (Green indicates areas of
almost no change in elevation. Warmer colors indicate the elevation
lowered. Cooler colors indicate areas of elevation increases, i.e.,
sediment deposition.)

Figure
16: Comparison of 1992 Elevations to 1998 Elevations.
The particle size distribution of
the deposited sediments was found by subjecting sediment samples to a
#200 sieve wash (Earth Systems Consultants, 1998). Samples were
collected from eroded streambanks, from the creek and overflow channel
beds, and from the surface of the floodplain. Particle-size data were
combined with topographic data to estimate the net deposition on site
for all sediments, and the net deposition for bed material. These
results are summarized in Table 3, and are compared to estimated
sediment loads from the watershed.
Table 3: Sediment
capture on Chorro Flats, 1992-1998, by particle-size
| |
All Sediment, tons |
Bed Material , tons |
| Load from watershed |
920,363 |
79,707 |
| Deposited on Chorro
Flats |
213,546 |
68,125 |
| Percent capture |
23% |
85% |
These figures show that
approximately 23% of the total load from Chorro Creek, and 85% of the
bed-load, was deposited on Chorro Flats between 1992 and 1998. A
significant amount of deposition occurred on site between 1992 and 1997
as a result of breaks in the levee, some naturally occurring, and the
one enlarged in 1994 through the EWP program to collect sediment
following the Highway 41 Fire. Significant deposition also occurred
during the El Niño winter, just months after construction was
completed.
It is expected that the long-term
sediment capture rates will be larger than these values because the
project wasn't completed until almost the end of this time period, and
because the trapping efficiency is expected to be greater now than it
was prior to project completion.
Available
Storage Capacity and Project Longevity
During the planning process for
the project (Crawford Multari &Starr, 1993), it was estimated that
the project would have 76 acres available for sediment deposition, with
a total storage capacity of 610,000 cubic yards (i.e., filled to a depth
of 5 feet.). Of that 76 acres, approximately 51 acres would be readily
available for sediment storage (because its elevation was below 20 ft.)
and could hold 247,000 cubic yards of material (i.e., filled to a depth
of 3 feet.) Assuming that 10,000 cubic yards of material would be
deposited per year, the project would remain effective at collecting
sediment for 61 years. It was also estimated that the project would
capture 20% of the silts and clays, 90% of the sands, and 100% of the
gravels and cobbles.
During the 6 years studied, it is
estimated that 188,000 cubic yards of material were collected.
Therefore, based on an initial capacity of 610,000 cubic yards, the site
has an available capacity of 422,000 cubic yards as of 12/31/99. If the
average sediment yield from the watershed is 60,689 tons per year
(69,000 cubic yards) (Tetra Tech, 1998), and the collection efficiency
remains at 23%, then approximately 15,870 cubic yards per year will
accumulate, filling the available capacity in 26 years.
Table 4. Estimates of
Project Longevity
| |
1993
estimate* |
1999
estimate** |
| Area
for deposition |
76
acres |
76
acres |
| Potential
storage (cubic yards) |
610,000 |
422,000 |
Sediment
load from watershed
(cubic yards per year) |
27,000 |
69,000
(Tetra Tech, 1998) |
| Trapping
efficiency |
26% |
23% |
Sediment
captured
(cubic yards per year) |
6,900 |
15,870 |
Years
needed to fill site
(based on 1993 watershed load
estimate) |
61
years |
|
Years
needed to fill site
(based on 1998 watershed load
estimate, Tetra Tech, 1998) |
34
years |
26
years |
* Crawford Multari and
Star, 1993
** Robbins and McEwen, 1999 |
Examining these data show that the
current estimate for sediment loads from the watershed is more than
twice the estimate used in 1993. Therefore it is not surprising that
although the project's trapping efficiency is similar to initial
predictions, the project is expected to collect sediment (and therefore
"fill up") more than twice as rapidly as initially planned.
It is worth mentioning that any
actions upstream of the Chorro Flats Enhancement Project which reduce
sediment loads to the creek will also serve to enhance the longevity of
this project. Specific actions could include implementation of
additional best management practices for sediment control or development
of additional sediment trapping areas (mini-Chorro Flats) further
upstream.
Riparian
Plant Community Development
The riparian plant community is
developing. Willow growth exceeds expectations. Other riparian plant
species are growing and will soon be large enough to persist without
additional maintenance.
During October, 1997, the banks of
Channels A, B, and C, and a 50 foot wide band adjacent to the banks,
were planted with a mixture of native trees and shrubs . A total of 340
shrubs and 1570 trees were grown in containers and transplanted on site.
An additional 8882 willow cuttings were planted (GANDA, 1998.) Plant
surveys conducted in 1998 and 1999 show that these trees and shrubs are
growing, and that a riparian plant community is developing. These plant
surveys and associated replanting efforts are discussed below.
In July and August, of 1998 and
1999, a survey of the planted areas was conducted to:
• determine how many plants
survived, and
• plan for the next season's
replanting effort.
Sixty-foot wide belt transects were
established perpendicular to the channels every 300 feet. Within each
belt transect, all surviving trees and shrubs which were planted as part
of this project were counted during each plant survey. Photographs were
taken at each transect for comparison purposes.
Plant survival results for all
planted tree and shrub species are summarized in Table 5.
Table 5. Plant
Survival Summary
| Species |
1997
Planted |
1998
Survival |
1999
Survival |
| Shrubs |
|
|
|
|
Twinberry
|
50 |
34% |
87% |
|
Wild Rose
|
75 |
47% |
71% |
|
Blackberry
|
46 |
2% |
126% |
|
Gooseberry
|
26 |
0% |
0% |
|
Hummingbird sage
|
24 |
0% |
0% |
|
Wax myrtle
|
14 |
63% |
14% |
|
Coffeeberry
|
66 |
53% |
55% |
|
Elderberry
|
39 |
80% |
74% |
|
Coyote bush
|
|
n/a |
n/a |
|
Total Shrubs
|
340 |
38% |
74% |
| Non-Willow Trees |
|
|
|
|
Red Osier Dogwood
|
211 |
117% |
90% |
|
Box Elder
|
11 |
0% |
55% |
|
Cottonwood
|
845 |
28% |
52% |
|
Live Oak
|
72 |
59% |
53% |
|
Sycamore
|
431 |
50% |
45% |
|
Total Non-Willow Trees
|
1570 |
63% |
55% |
| Total shrubs and
non-willow trees |
1910 |
59% |
58% |
| Willows |
|
|
|
| Red Willow |
3231 |
31% |
|
| Arroyo Willow |
5651 |
49% |
|
| Total Planted Willows |
8882 |
42% |
|
| Volunteer Willows |
0 |
|
|
| Total all Willows |
8882 |
256% |
|
A Note on Willow Survival
During the 1998 survey, it was noted that while the survival of planted
willow cuttings was approximately 43%. However, if "volunteer"
willow recruitment within the riparian band was included, the survival
percentage increased to 256%. (Approximately 8,000 willows were planted
in 1997, while in 1998 almost 23,000 willows were counted.)
Additionally, a large and uncounted number of willow stakes were planted
along the banks (as "willow mattresses", fascines,
"willow baffles", and as single stakes) during 1998 and 1999.
For these reasons, it was concluded that willow survival surpassed the
80% survival criteria required by the U.S. Army Corps. Therefore,
willows were not counted during the 1999 plant survey.
Replanting
In December, 1998, areas within the riparian zone were replanted with
1,066 shrubs and trees. Replanting efforts in 1998 were focused on
cottonwood and sycamore trees, with a lesser emphasis on shrubs and
other tree species. The overall survival rate of the 1998 replantings
was quite low. This low survival rate may be due in part to freezing
temperatures, which were encountered within days of replanting, and the
generally drier conditions found in spring and summer 1999.
Additional replantings were conducted in November 1999, and again in
February 2000. During these efforts, 1,135 trees and shrubs were
replanted. This replanting effort was intended to bring the number of
shrubs and trees to 120% and 117%, respectively, of the numbers planted
in 1997.
Development
of a Stable Stream Configuration
The stream is developing a
dynamically stable configuration. First-winter changes were significant.
Second-winter changes were much smaller. Future changes are expected to
be small because the banks are more thickly vegetated and therefore more
stable, and because the first-winter changes significantly increased the
flow capacity of the channel.
During the El Niño winter of
1997-98, the entire site was repeatedly flooded, and significant amounts
of sediment were deposited on the floodplain, within the old creek
channel, and within a secondary overflow channel. High flows spilled
into the overflow channel with such force that approximately 12,000
cubic yards of fine grained material eroded from the banks of the
upstream portion of the newly installed channel. The erosion lowered the
thalweg of the overflow channel so that the majority of the flow in
Chorro Creek now passes through the overflow channel, with the old creek
channel acting as an overflow channel. The predicted channel avulsion
occurred the very first rain season following construction.
The following photos show the
upstream end of the site, where significant erosion occurred during
early 1998, where willow fascines were planted in 1998 to protect the
bank, and where habitat improvement structures were installed in 1999.

Figure
17. Upstream end of "overflow" channel. November 1997.

Figure
18. "Overflow" channel at upstream end of project. February
1998.

Figure
19. Chorro Creek at upstream end of project. January 2000. Note habitat
improvement structures and willow wattle growth.
It should be noted that a
significant amount of channel realignment occurred immediately after
project construction during the "El Niño" winter of 1998. We
can expect that future annual changes in channel alignment will be
smaller than those of 1998 because:
- these high flows occurred when
the banks were relatively unprotected by vegetative growth;
- these banks are now partially
covered by riparian vegetation; and
- the erosion of 1997-98
significantly increased channel capacity, thereby reducing shear
stress on the banks.
Cross-sections of the old and new
channels were measured in late 1998. These cross-sections are compared
to available data regarding pre-1998 conditions, and are discussed
below. Cross-sections were not re-measured in 1999 because it did not
appear that significant changes in channel shape had occurred between
1998 and 1999. Cross-sectional re-measurements are planned for the year
2000, and thereafter at least once every 5 years, or every two years if
a 25-year storm has occurred during that time. Cross section locations
are shown in Figure 20.

Figure
20. Cross-section locations
Cross-sections measured in the upstream portion of the new channel show
significant erosion between 1997 and 1998. In this portion of the
project, the thalveg is from 4 to 2 feet lower than the bottom of the
overflow channel constructed in 1997. See Figure 21.