Chorro Flats Enhancement Project Final Report to the Prepared by the |
| The asterisks are hyperlinks to take your browser to the section indicated by "double-clicking". After viewing, click the "Back" button on your browser to return to this page. |
Introduction * Purpose of the Project * Scope of the Project * Problem Identification and Watershed Planning * Site Description * Site Acquisition * Project Planning * Interim Site Development * Project Implementation (Task 3) * Maintenance Chronology (Task 5) * Available Storage Capacity and Project Longevity * Riparian Plant Community Development * Development of a Stable Stream Configuration * Changes in Bankful Flow * Endangered Species Habitat * Beneficial Uses and Water Quality * Strategies for Long-term Monitoring and Maintenance 35 Long-term Conceptual Recommendations (Lessons Learned) 38 References * |
Table 1. Land use in the Morro Bay Watershed * Table 2: Estimated Sediment Loads to Morro Bay from Chorro Creek * Table 3: Sediment capture on Chorro Flats, 1992-1998, by particle-size * Table 4. Estimates of Project Longevity * Table 5. Plant Survival Summary * Table 6. 1999 MAPS Captures at Chorro Flats * Table 7. Desired Monitoring Activities * Table 7. Desired Monitoring Activities (continued) * |
Figure 1: Vicinity Map * Figure 2: Site Plan * Figure 3: Aerial Photo of Site and Vicinity * Figure 4: Simplified Chorro Flats fluvial processes, pre- and post-construction * Figure 5: Typical Plant Maintenance Procedure, May – June, 1998 * Figure 6: Willow Mattress - During Installation, May 1998, and after 4 months. * Figure 7. CCCs installing a willow baffle, September, 1998. * Figure 8. Irrigation continued in 1999. * Figure 9. Willow wattles installed in 1999. * Figure 10. Replanting in November, 1999. * Figure 11. Willow mattress installation 1999. * Figure 12: Instream Habitat Improvement Structures Installed in 1999. * Figure 13. Instream habitat structure installation, 1999. * Figure 14. Opposing wing deflector after installation. * Figure 15: Monthly precipitation between July 1992 and June 1998. * Figure 16: Comparison of 1992 Elevations to 1998 Elevations. * Figure 17. Upstream end of "overflow" channel. November 1997. * Figure 18. "Overflow" channel at upstream end of project. February 1998. * Figure 19. Chorro Creek at upstream end of project. January 2000. * Figure 20. Cross-section locations * Figure 21. Cross-sections from the upstream portion of the project * Figure 22. Cross-sections from the downstream portion of the project * Figure 23. Cross-sections from the old channel of Chorro Creek * Figure 24. Cross-sections from overflow channel "B" * Figure 25. Existing and designed channel bottom profile * Figure 26. Existing and designed channel capacity * Figure 27. 1998 maximum daily upstream and downstream temperatures * Figure 28. 1999 maximum daily upstream and downstream temperatures * Figure 29. Groundbreaking Ceremony July 9, 1997 33 Figure 30. Dedication Ceremony held 10-09-98 34 Figure 31. Lot Line Adjustment * Figure 32. Alternative Location for Channel Connection and Berm * |
|
Abstract The Chorro Flats Enhancement Project was implemented to reduce sediment loads to Morro Bay by allowing Chorro Creek to overflow on its original floodplain. The project has restored and enhanced 83 acres of wetland and wildlife habitat. The remaining 45 acres of prime farmland are used for agricultural production. This report summarizes site acquisition, planning, construction, maintenance and monitoring associated with the project, and serves as a "final report" for a grant administered by the Central Coast Regional Water Quality Control Board. A study conducted in 1988 showed that Morro Bay had been filling in at a rate ten times greater during the last one hundred years than it had previously. The major source of the sediment is the brushlands in Chorro and Los Osos Valleys. The Coastal San Luis Resource Conservation District, using funds provided by the California State Coastal Conservancy and Cal Trans, purchased the Chorro Flats site in 1991. Consultants prepared an Enhancement and Management Plan for the site. During all phases of the planning process extensive public input was encouraged. In 1994, a fire burned 35% of the Chorro Creek watershed in the steep brushy areas of the Santa Lucia Range. The Natural Resources Conservation Service improved the sediment trapping capability of Chorro Flats by creating a 450 foot breach of the levee. The most extreme floods of record followed this major fire the following winter, resulting in significant sediment deposition on Chorro Flats. The State Water Resources Control Board, the California Coastal Conservancy, and Cal Trans provided funding for construction and maintenance costs. Work began in July of 1997, and was completed in late November. During the El Niño winter of 1997-98, the entire site was repeatedly flooded, and significant amounts of sediment were deposited on the site. This first-year deposition, when combined with the deposition from the 1995 floods and all the other minor floods since 1992, brought the net total amount of sediment captured on the site to 188,000 cubic yards. During early 1998, approximately 12,000 cubic yards of fine grained material (equal to about 6% of the net amount collected on site between 1992 and 1998) eroded from the banks of the upstream portion of the newly installed overflow channel. This erosion lowered the thalweg of the overflow channel so that the majority of the flow in Chorro Creek now passes through the overflow channel, with the old creek channel now acting as an overflow channel. In 1998, the California Conservation Corps performed the initial maintenance on planted materials: checking each plant location and condition, hand weeding, clearing, building irrigation basins, watering, and placing mulch. Other maintenance activities have included installation of "willow mattresses" and other riparian tree species by CalPoly students, application of herbicide to control undesirable weed species, replanting of some grasslands, periodic mowing of the grasslands, and additional willow plantings along the banks of the creek. Additional trees and shrubs were installed in late 1998 and late 1999 to replace plants that had not survived. Raptor perches have been installed within the riparian zone along Chorro Creek to enhance rodent control. During September and October 1999, 12 log and boulder structures were installed in the upstream portion of the project to improve steelhead trout summer rearing habitat. The work was partially funded by a $30,000 CDFG fisheries restoration grant. Approximately 23% of the total load, and 85% of the bed-load, from Chorro Creek between 1992 and 1998 was captured on Chorro Flats. The current estimate for sediment loads from the watershed is more than twice the estimate used in 1993. Based on the revised annual sediment load, and the 23% trapping efficiency, it is expected that the Chorro Flats site will fill in 26 years. Any actions upstream of the Chorro Flats Enhancement Project that reduce sediment loads to the creek will also serve to enhance the longevity of this project. Specific actions could include implementation of additional best management practices for sediment control or development of additional sediment trapping areas (mini-Chorro Flats) further upstream. The stream is developing a dynamically stable configuration. First-winter changes were significant. Second-winter changes were much smaller. Future annual changes are expected to be small because the banks are more thickly vegetated and therefore more stable, and because the first-winter changes significantly increased the flow capacity of the channel. In July and August, of 1998 and 1999, a survey of the planted areas was conducted. The riparian plant community is developing. Willow growth exceeds expectations. Other riparian plant species are growing and will soon be large enough to persist without additional maintenance. Habitat suitable for endangered species is being created. Pools and riffles are developing. Steelhead and red-legged frogs have been found on the site. Water temperature in Chorro Creek at the upstream and downstream ends of the project were measured in 1998 and 1999. In both years, downstream temperatures are generally higher than upstream temperatures. This increase is generally between 3 and 5 ° F, with a maximum increase of almost 8 ° F. A Monitoring Avian Productivity and Survivorship (MAPS) monitoring station was set up on the Chorro Flats site in 1999. Initial results indicate that the site provides habitat for a wide variety of birds. Numerous public education opportunities have been provided at the site, via the media, and via various public forums. It is expected that within the next two years a suitable agency will be identified and will agree to assume ownership and responsibility for the maintenance of the wetland portion of the site. Numerous suggestions are presented regarding lessons learned during the project. The suggestions focus on the planning process, the contracting process, alternative locations for the channel and the berm, and ways in which an "adaptive management" approach could have benefited the project. This document and additional information regarding conservation projects undertaken by the Coastal San Luis Resource Conservation District can be found on the web at www.coastalrcd.org. |
| Note: The graphics on this page have been reduced to thumbnail images to facilitate loading of this page. It may take three to five minutes to load, depending on the speed of your computer. If you wish to view the larger version of an image, "double click"on the image. After viewing or printing the image, click the"Back"button on your browser to return to this page. |
|
Figure 21. Cross-sections from the upstream portion of the project Cross-sections measured in
the main channel in the downstream portions of the project show much
less realignment than those in the upstream portion of the project.
Thalveg elevations are much closer to channel bottom elevations
constructed in 1997 than those found in the upstream portions of the
project and the banks show very little erosion. See Figure 22. Figure 22. Cross-sections from the downstream portion of the project Cross sections measured in the old
Chorro Creek channel show a mix of erosion and deposition. See Figure
23. Figure 23. Cross-sections from the old channel of Chorro Creek Cross sections measured in
overflow channel "B" show significant amounts of
sedimentation. See Figure 24. Figure 24. Cross-sections from overflow channel "B" Channel development during the first two seasons of the project resulted in changes to channel capacity. These changes have therefore affected the flow rates that will result in overbank flow, thereby possibly changing the trapping efficiency of the project. To analyze these changes, the new channel bottom elevation profile has been compared to designed elevations and existing channel capacities have been compared to designed channel capacities. (Channel capacities were estimated using a Mannings "n" of 0.035.) These parameters are displayed in the following figures, and are discussed below. Figure 25 clearly shows the downcutting that occurred in the upstream portion of the site. This downcutting, and associated channel widening, has resulted in increased channel capacity in this region, as can be seen in Figure 26. Figure 25. Existing and designed channel bottom profile Figure 26 clearly shows that the middle and more downstream portions of the site will experience more frequent flooding than the upstream third of the site. This conclusion is supported by field observations during flood events, and by topographic data. This figure also shows that the upstream portions of the site are expected to flood less frequently than initially designed. It should be noted here that the 2-year flood flow rate shown in Figure 26 refers to all of Chorro Creek at Chorro Flats, including flows in all overflow channels. Therefore, the "local" flow rates which would be expected in the new channel on a two-year return frequency are lower than the "2-year flood" value shown in Figure 26. Figure
26. Existing and designed channel capacity Habitat suitable for endangered species is being created. Pools and riffles are developing. Steelhead and red-legged frogs have been found on the site. A fish habitat survey was conducted in June and July, 1998, by the California Department of Fish and Game. They found 7% of the length of Chorro Creek surveyed to contain pools and 6% to contain riffles (Nelson, 1999). The remaining 87% was classified as open water. 80% of the pools were over 3 feet deep. Another fish habitat survey is planned for July 2000. We expect to see an increase in the amount of pool habitat, in part due to natural channel forming processes, and in part due to scouring associated with the instream habitat structures that were installed in 1999. For example, the largest pool on the project site formed downstream of a root-wad that was installed in 1997. A large number of fish were regularly observed within this pool during the summer of 1999. During the fish habitat survey in 1998, CDFG personnel also sampled fish populations. They found six individual steelhead in Chorro Creek. One 5-inch steelhead was found near the center of the project and five 10-inch steelhead were found near the upstream boundary of the project (Highland, pers. comm., 2000). In 1997 no CRLF were found on the project site during surveys conducted in July and August (Garcia and Associates, 1998.) During August, September, and October, 1999, California red-legged frogs (CRLF) were found in Chorro Creek in the upstream portion of the project as part of monitoring associated with installation of instream habitat improvement structures (Wilcox, 1999, and Morro Group, 1999.) Therefore, it appears that habitat suitable for this species is being created. Beneficial Uses and Water Quality Aquatic and riparian habitat beneficial uses are being enhanced. Water quality is being improved by reducing sediment loads to Morro Bay. However, riparian vegetation will not provide significant shading, and assumed improvements in temperature, for several years. The enhancement of habitat values and the reduction in sediment loads are discussed above. Water temperatures upstream and downstream of the site have been collected to document temperature changes within the project, and are discussed below. Use of the site by migratory birds has also been monitored, and is also discussed below. The data show little difference between the periods studied. In both years, downstream maximum temperatures are generally higher than upstream maximum temperatures. This increase is generally between 3 and 5 ° F, with a maximum increase of almost 8 ° F. Larger temperature increases tended to occur when upstream temperatures were higher. This correlation is reasonable; on hotter days we expect higher temperatures at the upstream end and we also expect greater warming as the creek flows through the project.
Table
6. 1999 MAPS Captures at Chorro Flats
Public Participation Opportunities Numerous public participation opportunities have been provided at the site, via the media, and via various public forums. These activities are listed below. A public meeting was held at the San Luis Obispo County Planning Commission Hearing on February 13, 1997 to describe the project and inform the public. A responsiveness summary was prepared that summarized the views and comments received during that meeting, and specific responses to those comments. A groundbreaking ceremony and news conference was held on July 9, 1997. Figure 29. Groundbreaking ceremony July 9, 1997. Weekly meetings were held during construction with CSLRCD and NRCS staff, contractors, subcontractors, suppliers, and members of the Technical Advisory Committee. Interpretive signs were developed and installed at the Quintana Road overlook and at the Black Hill overlook. Figure 30. Dedication ceremony held 10-09-98. A dedication ceremony and news conference was held October 10, 1998. A memorial plaque for Russ Whitaker was installed on the boulder adjacent to the interpretive sign on Quintana Road. Approximately 40 people attended the ceremony, including Cathy Novak, the Mayor of Morro Bay, Bud Laurent, a San Luis Obispo County Supervisor, as well as representatives of Congresswoman Lois Capps, and Assemblyman Tom Bordonaro. Many people participated in a site tour that was offered immediately after the ceremony. The dedication ceremony was videotaped and aired on local public television. In January 1999, a summary of data available regarding deposition on the site was developed. This material was presented to local reporters and to the Morro Bay City Council and to the Morro Bay National Estuary Watershed Committee. A press release regarding sediment deposition on site was developed and distributed to the local media. In early 1999, a paper regarding the project was presented at Urban Streams Conference, and was also posted to the CSLRCD web page (www.coastalrcd.org). A presentation on Chorro Flats was delivered at the Urban Streams Conference (4/12/99). Conference attendees toured the site on 4/11/99. Public "nature-walks", held on the 4th Saturday morning of each month, began in May 1999. These walks have had good attendance. Topics have included wildflowers, bird monitoring activities, and comparison of pond and stream ecology. During 1999, tours of site were given to interested groups including Monarch Grove Elementary School, Foundation K'sh, Greenspace North Coast Summer Youth Work/Study Program, California Regional Water Quality Control Board TMDL workshop, National Non-point Source Monitoring Workshop, and Friends of the Estuary general meeting. In September 1999, preliminary monitoring results were presented at the National Non-point Source Monitoring Workshop in Morro Bay. In 1999 a vegetation survey of the
grasslands portion of the site was completed as a Senior Project by a
Cal Poly student, Crystahl Handel. Strategies for Long-term Monitoring and Maintenance Long-term Maintenance and Monitoring Needs Various types of long-term maintenance will be required for the site, and are discussed below. Required Monitoring Monitoring is required to meet the terms of several permits and grants associated with the project. These requirements are discussed below. The initial permit was for the construction of the entire project, as implemented in 1997. This permit requires that plant surveys be conducted at least annually until 80% of the planted trees and shrubs survive. We anticipate that this survival target will be met in July 2000, and plant surveys will not be required after this time. An additional permit was issued for installation of instream habitat improvement structures in 1999. Monitoring reports are required by August 31 of each year for three years. These reports will contain monitoring results, photographs, a description of maintenance activities, an assessment of attainment of performance criteria. If all success criteria are met before August 31, 2002, a final annual report will be produced and will serve as a completion report. Additional instream habitat structures are planned for installation in 2000 and 2001. It is anticipated that the monitoring requirements for these structures will be similar to those discussed above. If this is so, then there may be monitoring requirements that extend until 2004. Desired Monitoring Additional monitoring efforts were described in the Monitoring and Maintenance Plan. While these monitoring activities are not required, per se, they would provide information that may be useful in assessing the success of the project and in planning similar projects. These monitoring activities are listed below. Table
7. Desired Monitoring Activities
Table
7. Desired Monitoring Activities (continued)
Land Ownership A lot line adjustment has been made so that the site now consists of three parcels. See Figure 31 below. Figure 31. Lot Line Adjustment The agricultural portion of the site has been split from the wetland portion of the site (Parcel 3). The agricultural portion has been split into two separate parcels at the access road. Both the agricultural parcels (Parcels 1 and 2) also include the berm on their southern border. The reason for this lot line adjustment was so that the wetland portion of the site could be transferred to some other agency for long-term ownership while the agricultural portion could be retained in agricultural production. It is expected that within the next two years a suitable agency will be identified and will agree to assume ownership and responsibility for the maintenance of the wetland portion of the site. Potential agencies include California State Parks and the U.S. Fish and Wildlife Service. The agricultural parcels may be retained by the CSLRCD, or they may be used in some sort of a real estate transaction which would allow the CSLRCD to acquire other lands to implement additional soil and water conservation practices. Funding Currently, the site generates approximately $9,000 in annual income - $6,000 from the lease on the radio towers on the western portion of the property, and approximately $3,000 from leasing the agricultural portion of the site. This amount may be sufficient for routine, small-scale weed abatement activities and periodic maintenance of other site features. It is not clear whether this amount is sufficient to meet all maintenance and monitoring needs of the site over the long term. At the present time, no other long-term funding source has been identified. Long-term Conceptual Recommendations (Lessons Learned) Regional Water Quality Control Board staff have requested that this report contain long-term conceptual recommendations; in other words, a distillation of our experiences with the project, with a view to providing guidance to similar efforts. The following recommendations are offered to enhance the success of projects similar to the Chorro Flats Enhancement Project (CFEP), and are not meant as criticism for any of the individuals who have contributed to this project. The project is highly successful at meeting its objectives, and the people who have worked on it should be congratulated for their worthwhile efforts. Management However, it should be realized that the burdens of this long planning effort often fell to community members acting without compensation. Therefore, unless a community contains a number of dedicated individuals, willing to spend long hours at meetings, dealing with paperwork, etc., worthy project such as the CFEP may never be planned, and therefore never implemented. Therefore, it is recommended that planning efforts receive adequate funding, or some other way be found to encourage and support "volunteers" who work to plan these sort of projects. It may have been more appropriate to break the project into distinct phases and pay the withholding for each phase as it was completed. For example, the project could have been broken down into separate phases for construction and for each year of maintenance. In this way a large, multi-year project could be undertaken by a relatively small organization without the need for additional funding to cover the 10% shortfall which builds up as the project progresses. Project Design Additionally, the connection between the overflow channel and Chorro Creek was made at the extreme upstream end of the site. However, connecting to Chorro Creek at this location, in conjunction with the erosion noted above, has resulted in significant erosion very close to the berm and somewhat close to the high voltage power transmission towers that cross the site. A preferable location for the connection may have been somewhat further downstream, to avoid potential impacts to the berm and towers. See Figure 32. Figure 32. Alternative Location for Channel Connection and Berm It is important to highlight the sequence of extraordinary storms/winters that occurred following project design and sequential implementation. These storms were much more severe than would have been predicted based on longer term averages. Some of the benefits (i.e. rapid trapping of sediment), and problems (e.g., the immediate avulsion of the creek out of the old channel to the new, small, 2-year pilot channel), are related to these big events. In project planning, you always try and develop a plan that can accommodate these larger, unexpected events (as the CF project has), but nature is unpredictable. In particular, it was expected that the shift to the new pilot channel might occur gradually, over decades, by which time a dense vegetation cover would be established and problems of erosion (particularly near the power tower) would not have developed. This was the most serious problem that was not handled well in the design, in retrospect. (Haltiner, pers. comm., 2000) Conversely, the easterly end of the floodplain portion of the project is higher and drier than the rest of the site, and receives floodwaters (and sediment) less frequently. These observations lead to the suggestion that a better location for the berm may have been closer to the creek in the easterly portion of the site, and further from the creek in the westerly portion of the site. See Figure 32. However, it should be noted that recent years have been the exceptionally wet, and that prior to project implementation the western areas of the site were usually left fallow during very wet years. Additionally, material excavated from the "pilot channel" and from the old levee on Chorro Creek was spread over this portion of the site, thereby raising its elevation and improving drainage. During planning, an alternative was considered where no berm would be built, but that the wetland portion of the site would be sloped gently upward to the (higher) agricultural portion of the site. It has been suggested that the agricultural portion of the site might drain better if it had been sloped, rather than separated with a berm (Worcester, pers. comm., 2000). However, a berm was used for the following reasons: · During moderate flood events the berm would prevent floating debris from washing onto the agricultural fields, and during large flood events would also keep large grained sediments out of the agricultural fields. Exclusion of these materials would benefit agricultural operations. Because the upstream connection between the existing creek and the "overflow" channel eroded more quickly than expected during the first winter, Chorro Creek is now in a "new" location. Forcing Chorro Creek back into its old location has been considered. However, leaving Chorro Creek in its present location is preferable because the new channel provides better habitat for steelhead, and because forcing all the flow back to the old channel would effectively "dewater" the new channel - an action that could not be permitted. There is a related concern that the old channel would dry up before California red-legged frog tadpoles could reach maturity. However, this concern has proved groundless because a small amount of water has been observed flowing into the old channel during late spring and early summer in 1998 and 1999. Implementation This project was fortunate to have a significant amount of resources allocated for monitoring and maintenance. However, in planning future projects, it may be wise to consider applying an adaptive management strategy from the beginning. This strategy would result in a phased implementation approach, periodic re-evaluations to provide "feedback", and an evolving set of "success" criteria. It is important to note that adaptive management processes will not always neatly match funding or permitting criteria. The following discussions highlight how an adaptive management approach would benefit this project. Perhaps a better strategy would have been to build an overflow channel without removing the levees. Then spend several years establishing the bank vegetation and floodplain vegetation. After two years, the levees could have been removed (with minimal disturbance to the new channel and associated vegetation) and the berm could have been constructed. Then, when the first year floods arrived, the waters would flow into a more protected channel. This recommendation obviously would require project implementation be phased over several years, thereby reducing the amount of sediment which could be captured during the first years. However, because the project was envisioned with a 50 to 70 year lifespan, a delay of a few years may not be significant. It should be noted that an early recommendation called for creating a new, full-scale channel in the historic channel location, revegetating it for about 5 years, then excavating a connection and plugging the old channel (Crawford Multari & Starr, 1993). However, at the time, there were three areas of opposition to this approach (Haltiner, pers. comm., 2000): · Geomorphologists involved with the project felt that any new channel would likely be unstable (over a time-frame of centuries), so excavating a new one would not likely be of much benefit. · It was believed that a permit to block the old channel would not be issued, due to endangered species issues. · During initial design work, there was no clear long-term site manager/entity identified that could guarantee that the 5-year planting/monitoring, then breaching of the opening would all occur. So it was decided to do an "all-in-one" restoration project, with a smaller emphasis on longer-term maintenance and monitoring. In retrospect, a more sequential and "adaptively managed" approach may have been more effective. · Funding agencies involved with the project were unwilling to support a phased approach. They needed to spend their money by a certain date or it would be re-allocated to other projects (Scott Robbins, pers. comm., 2000). Maintenance When trees and shrubs were first replanted in December 1998, the areas that were to be replanted were rototilled before the plants were installed. However, this rototilling appears to have encouraged weed growth over the desired grass species. Therefore, it is not recommended that areas previously seeded to grass be tilled, unless additional grass seed is also being applied. During the first growing season,
little was done to control weeds in the grassland areas. The more
noticeable and invasive species were removed by hand. Mowing was
undertaken once, at the end of the season. In the few areas that were
mown early during the first summer, grass growth the following season
was significantly better than in non-mown areas. Therefore, it is
recommended that regular mowing be incorporated in areas where grasses
are planted. References (Chronological Order) Haltiner, Jeff, 1988, Sediment Processes in Morro Bay, California, prepared by Philip Williams & Associates, Ltd. for the Coastal San Luis Resource Conservation District (CSLRCD) and the California State Coastal Conservancy (CSCC). USDA SCS, 1989, Erosion and Sediment Study, Morro Bay Watershed, prepared for the CSLRCD and the CSCC. __________, 1989, Morro Bay Watershed Enhancement Plan, prepared for the CSLRCD and the CSCC. Arnold, Carol, 1991, Project Summary, California State Coastal Conservancy Crawford, Multari & Star; Jones and Stokes Associates (JSA); Philip Williams & Associates (PWA); Habitat Restoration Group, 1993, Existing Conditions Background Report, Chorro Flats Enhancement and Management Plan, prepared for the CSLRCD and the CSCC. ________________, 1993, Analysis of Options and Alternatives Report, Chorro Flats Enhancement and Management Plan, prepared for the CSLRCD and the CSCC. ________________, 1994, Conceptual Plan, Chorro Flats Enhancement and Management Plan, prepared for the CSLRCD and the CSCC. PWA; JSA; Crawford, Multari & Star; Engineering Development Associates (EDA), 1996, Conceptual Plan Refinements/Final Design Issues, Chorro Flats Enhancement and Management Plan, prepared for the CSLRCD and the CSCC. EDA; JSA, 1997, Construction Drawings and Specifications for the Chorro Flats Enhancement Project, prepared for the CSLRCD and the SCC. Garcia and Associates, 1998, Chorro Flats Enhancement Project California Red-legged Frog Preconstruction Survey and Monitoring Results Report, prepared for the CSLRCD Garcia and Associates, 1998, Chorro Flats Enhancement Project Revegetation Support Services, prepared for the CSLRCD. Earth Systems Consultants, 1998, Results of #200 sieve wash, November 15. Tetra Tech, 1998, Sediment Loading Study, Morro Bay National Estuary Program. CSLRCD, 1998, Chorro Flats Monitoring and Maintenance Plan, CSLRCD. Vaughan Surveys, 1999, topographic data and associated calculations, Bryce Dilger - Land Surveyor, prepared for the CSLRCD. Robbins, Scott and Malcolm McEwen, 1999, Chorro Flats Enhancement Project, paper presented at the Urban Streams Conference, April 12, 1999. Nelson, Jennifer, 1999, Results of Habitat Assessment in Chorro Creek, California Department of Fish and Game. Wilcox, Glenn, 1999, Results of Field Survey for California Red-legged Frogs on the Chorro Flats Property, Natural Resources Conservation Service. Morro Group, Inc., 1999, Chorro Creek Instream Habitat Improvement Project Completion Report, prepared for the CSLRCD. Handel, Crystahl, 1999, Grassland Survey of Chorro Flats, prepared as a senior project for California State Polytechnic University at San Luis Obispo. Highland, David, 2000, personal communication, Results of Electro-fishing Conducting in Chorro Creek in July, 1998, California Department of Fish and Game. Worcester, Karen, 2000, personal communication, California Regional Water Quality Control Board, Central Coast Region.
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||